Govt to revive Dabhol power plant Illustrative image – not actual.

The government is looking forward to reviving a Dabhol power project in Maharashtra.

 

It is working out four options to provide gas to run the 1,967 MW power project, which otherwise will turn into a non-performing asset soon for not being able to repay loans. These different options that may be acceptable to all stakeholders will be subject to the final approval from the Cabinet Committee on Investment or the empowered group of ministers (eGoM).

 

The project has been facing a shortage of gas since September 2011. The company requires gas in multiples of 1.4 million standard cu mtr per day to run each gas turbine.

 

For ensuring debt servicing and operating and maintenance expenses, the project requires to run at least four out of the six gas turbines on a continuous basis.

 

The second option is to pursue the Maharashtra government to purchase electricity generated from R-LNG (imported gas) for ensuring the project's viability and pay the corresponding fixed cost.

 

The third option is diverting gas from a non-core sector to the power plant.

 

The last option is to pool Administered Price Mechanism (APM) and non-APM gas in the power sector.

 

Ratnagiri Gas and Power Private (RGPPL) has been defaulting on its debt servicing payments since September 2013, due to its inability to recover fixed cost; it faces the prospects of turning into an NPA.

 

NTPC and GAIL hold 32.86 per cent each in RGPPL. MSEB Holding has 17.41 per cent and the remaining 16.87 per cent is held by financial institutions such as IDBI, SBI, ICICI Bank and Canara Bank.