Illustrative image – not actual.The Union Power Ministry has shelved the ultra mega power project (UMPP), at Surguja in Chhattisgarh due to environmental issues.
The Ministry has dropped the 4,000 MW project due to the uncertainty in allotment of coal block to the project, on environment issues. The UMPP has been allotted Hasdeo-Arand coal blocks which fall under the area of dense forests and were classified by the Ministry of Environment & Forests as 'no go' as they could have an adverse impact on the environment.
As per the guidelines of Central Electricity Regulatory Commission, the exploration work at the coal blocks allotted for the ultra mega power projects should have started within 730 days of the Coal Ministry's approval. This deadline expired in March 2012.
In addition, the tendering process for the project had been delayed many times in the past due to lack of environment clearance for the allotted coal mines.
The project, estimated to cost Rs 20,000 crore, is being developed by Chhattisgarh Surguja Power (CSPL), a wholly owned subsidiary of Power Finance Corporation (PFC).