Govt of Nigeria to restore critical transmission power linesIllustrative image – not actual.
The Transmission Company of Nigeria (TCN) is set to restore seven critical transmission lines across the country. The government of Nigeria aims to raise transmission wheeling capacity to 10,000 MW by the end of 2019.

To attain 10,000 MW, TCN is procuring quad conductors, a high capacity conductor that could carry more bulk power capacity on the same transmission line. The seven critical lines include Onitsha-Awka-Oji River lines, the Ikeja West-Alimosho-Ogba-Ota line, and the Alimosho-Alausa line.

The rest are, Kaduna-Zaria-Funtua-Gusau line, Birnin Kebbi-Sokoto, Aba-Itu, and Kumbotso-Dan Agundi 132 kV transmission line. Upon completion of transmission lines re-conductoring projects, are going to between 2,000 MW and 3,000 MW which means the grid will shift from 8,100 MW to at least 10,000 MW.