Illustrative image – not actual.To attain 10,000 MW, TCN is procuring quad conductors, a high capacity conductor that could carry more bulk power capacity on the same transmission line. The seven critical lines include Onitsha-Awka-Oji River lines, the Ikeja West-Alimosho-Ogba-Ota line, and the Alimosho-Alausa line.
The rest are, Kaduna-Zaria-Funtua-Gusau line, Birnin Kebbi-Sokoto, Aba-Itu, and Kumbotso-Dan Agundi 132 kV transmission line. Upon completion of transmission lines re-conductoring projects, are going to between 2,000 MW and 3,000 MW which means the grid will shift from 8,100 MW to at least 10,000 MW.