The government has relaxed qualification norms for those interested in bidding for ultra mega power projects (UMPPs).

 

The Power Finance Corporation had floated tenders for qualification in September 2013 for two UMPPs. These two are: Cheyyur UMPP in Tamil Nadu which is based on imported coal; and the Orissa UMPP which will run on domestic coal. These two projects entail investments of over Rs 50,000 crore. The relaxation is expected to help infrastructure players compete with power companies in the bids for UMPPs.

 

As per the new norms, the total capital cost requirement, in order to qualify for setting up the plant, has been brought down to five per cent and the expenditure incurred by the companies on projects in the past seven years will be counted, as against the five years specified earlier. Previously, the criteria had been kept at 10 per cent of the proposed project.

 

In addition to this, the fuel cost will be finalised at the request for proposal stage, as against the earlier norm of finalising it at the RfQ stage. This has been decided in order to allow companies to make error-proof bids after calculating the risks involved in the project.

← All latest storiesBack to top →