Government to spend Rs.4,457 crore on DMR Project during Tenth PlanIllustrative image – not actual.

The Government plans to incur a capital expenditure of Rs.4,456.82 crore on the Delhi Metro Rail Project during the Tenth Plan Period (2002-07). The project is being implemented by Delhi Metro Rail Corporation (DMRC). The 52 km first phase of the Delhi Metro Rail Project is estimated to cost Rs.8,000 crore and scheduled for completion by September 2005.

 

The project has a debt to equity ratio of 7:3. The Central and Delhi state governments, besides splitting the equity, are providing 8 per cent of the project cost as interest free loans. Japan Bank for International Corporation (JBIC) is funding the project to the extent of 56 per cent of the total project cost. The balance 6 per cent would be met through property developments.

 

Of the Rs.4,456.82 crore investment for the Tenth Plan, Rs.4,035.63 crore will come as assistance against the JBIC loan while Rs.418.19 crore will be in the form of equity from both the central and state government. A subordinate debt of Rs.3 crore will also be availed. It may be noted that three tranches of JBIC loan amounting to Rs.470 crore, Rs.276 crore and Rs.1,035 crore have already been arranged so far.

 

Meantime, DMRC is preparing a revised cost estimate for the project based on replacement of Trinagar-Nangloi corridor in north-west Delhi with a corridor connecting Connaught Place in central Delhi to the new township of Dwarka in west Delhi. The revised estimate would be put up for government approval shortly. The project has undergone many revisions due to the frequent changes in the alignment (routes) of various corridors.

← All latest storiesBack to top →