Illustrative image – not actual.The Union Government has planned an outlay of Rs 250 crore for the ongoing as well as new road projects on various National Highways in Uttar Pradesh during the current fiscal.
A detailed project report is reportedly in progress for the Delhi-Meerut Expressway. The construction on the Meerut-Muzaffarnagar section (NH-58) is in progress under Phase-III of NHDP on BOT basis. About 51 km road of the 78 km stretch has been completed. The project is slated to be completed by March 2010.
The Government is likely to re-invite bids on BOT (Toll) basis for Muzaffarnagar to Haridwar section. This section had been identified for 4-laning under NHDP Phase-III and bids were invited twice earlier but no response was received from bidders.