The Union Government on 4 July 2009 cancelled coal linkages of captive power plants with a combined capacity of 1,292 MW. These units require 5.844 million tpa of coal.
Despite a considerable lapse of time, companies failed to set up power plants in spite of having been accorded coal linkage by the ministry between 1996 and 2006.
According to sources, in seven cases appropriate directions have been issued for signing the fuel supply agreement, while in the remaining 19 cases, CIL has been asked to send letters asking them to give detailed project status within 15 days failing which linkage will be cancelled without any further notice.
The ministry has already served de-allocation notice on 14 coal properties. Most of these 25 power plants that lost coal linkage were located in Chhattisgarh, Jharkhand, and Maharashtra.