Illustrative image – not actual.In view of the decline in production of
capital goods in the first five months of the current fiscal year, the
Confederation of Indian Industry (CII) has urged for early completion of
infrastructure projects.
The
Project Monitoring division of the Ministry of Statistics & Programme
Implementation has stated in its annual report that nearly 45 per cent of the
437 projects undertaken by the Central government had experienced a time
overrun as on 1 November 1999. With the result, the cost of these projects is
expected to rise from the original Rs.1,31,606 crore to around Rs.1,54,405 crore.
The Railways, the annual report stated, had the largest number of incomplete projects followed by coal, surface transport, petroleum and petrochemicals and power.
The
cost overrun resulting by the delay in implementation is likely to affect the fertilizer
sector the most. It is estimated that this sector would have to suffer a 42.7
per cent increase in capital expenditure due to the time overrun. Some other
sector that would be similarly affected include atomic power (31.2 per cent
increase in project cost), surface transport (29 per cent), steel (25.6 per
cent), power (20.3 per cent) and railways (20.2 per cent).
The
CII has identified 53 projects to be taken up with top priority. These include
the power projects of Kawas II and Gandhar by National Thermal Power
Corporation (NTPC) in Gujarat and the Rayalseema Power Project by the Andhra
Pradesh State Electricity Board.