Illustrative image – not actual.The Cabinet Committee on Infrastructure (CCI) has cleared road projects spread across Orissa, Andhra Pradesh, Uttar Pradesh, Karnataka, Maharashtra and, Rajasthan.
The road projects worth Rs 9,620 crore are to be implemented under DBOFT on BOT toll mode under NHDP phases II, III, IV and V.
| Name of the Project | Legnth (in km) | Cost (Rs Crore) | State | Concession Period (in years) | Completion Period (in months) |
| Six laning of Chandikhole – Paradeep section of NH 5 A under NHDP Phase-V | 76.618 | 1,014.36 | Orissa | 30 | 30 |
| Six laning of Gundugolanu - Rajahmundry section of NH 5 under NHDP Phase-V | 120.741 | 1,766.25 | Andhra Pradesh | 24 | 30 |
| Four laning of Ghaghar Bridge (Indo Nepal Border) - Varanasi section of NH 233 under NHDP Phase-IV | 177.555 | 1,895.95 | Uttar Pradesh | 24 | 30 |
| Four laning of Sultanpur – Varansi section of NH 56 under NHDP Phase-IV | 154.950 | 1,564.73 | Uttar Pradesh | 20 | 30 |
| Four laning of Hoskote – Dobbaspet section of NH 207 under NHDP Phase-IV | 80.020 | 1,153.30 | Karnataka | 30 | 24 |
| Four laning of Solapur – Bijapur section of NH 13 in Maharashtra and Karnataka under NHDP Phase-III | 110.542 | 1,091.89 | Maharashtra & Karnataka | 20 | 30 |
Further, the CCI approved the implementation of development (through four laning) and operation of Sikar - Bikaner section of NH 11 from km 340.188 to km 557.775 via Sikar bypass and Bikaner bypass from km.553.869 of NH 11 to km 267.325 of NH-89 in Rajasthan with two lane with paved shoulders through public private partnership on DBFOT basis. The total cost of the project will be Rs 632.54 crore out of which Rs 5 crore will be towards cost of land acquisition, rehabilitation, resettlement and pre construction. The total length of the project will be 237.578 km.
Also, the CCI has approved the implementation of development (through four laning) and operation of Zirkapur - Patiala section (50.7 km) of NH 64 in Punjab through PPP on DBFOT basis. The total cost of the project will be Rs 501 crore out of which Rs 79.22 crore will be towards cost of land acquisition, rehabilitation, resettlement and pre construction. The concession period will be 14 years. The total length of the project will be 50.70 km.