The Blueprint for Power Sector Development brought out by the Union Ministry of Power has fixed power capacity addition at 46,185 MW during the 10th Plan and 60,885 MW during the 11th Plan. This is in an attempt to meet the objective of ‘power on demand’ by 2012.

 

Power capacity to be added by the Central and state government utilities and the private sector are given in the table below:

                                                                                                                          

 

Power Capacity to be Added (MW)

10th Plan

11th Plan

Central Govt Owned Utilities

28,485

36,785

State Govt Owned Utilities

8,300

10,600

Pvt. Sector Companies

9,400

13,500

 

Of the total power to be added by central power utilities, it is expected that National Thermal Power Corporation and National Hydroelectric Power Corporation would add 23,000 MW during the 10th Plan and 23,500 MW in the 11th Plan.

 

An investment of around Rs.8,00,000 crore has been estimated to create additional power generation capacity of 1,00,000 MW and build the necessary transmission and distribution infrastructure during the two Plan periods by 2012.