Government clears REL's two transmission projectsIllustrative image – not actual.

The government has cleared Reliance Energy's Rs.3,500 crore two transmission line projects - western region system strengthening (WRSS) II and the Parbati-Koldam hydro projects in Himachal Pradesh.

The two projects had been delayed due to issues raised by the public-private partnership appraisal committee (PPAC). Now issues regarding buyout and transfer of the projects are resolved as REL accepted PPAC's suggestions and has agreed to abide by PPAC's suggestions. The agreement is likely to be signed by end September 2007 or early October 2007.

The transmission lines of Parbati and Koldam projects, both 1,600 MW projects of the National Hydroelectric Power Corporation (NHPC) and the NTPC, had been delayed for almost two years now, while the 4,000 MW WRSS II, a power evacuation project, has been delayed for 10 months.

Power Grid Corporation of India (PGCIL), the nodal agency for both WRSS and Parbati-Koldam, had selected private partner for the projects through the international competitive bidding process. For Parbati-Koldam, PGCIL had invited bids in November 2004 and final letter of selection was issued in December 2005. REL and PGCIL had floated a 74:26 joint venture for the Rs.1,500 crore projects.

Reliance Energy Transmission (RETL), a subsidiary of REL, had bagged the Rs.2,000 crore WRSS II project. The bidding process was completed by end-2006 and the project is scheduled to be commissioned by March 2010.