Gosikhurd irrigation project to get over by 2022Illustrative image – not actual.

The Vidarbha Irrigation Development Corporation (VIDC) has filed an affidavit before the Nagpur bench of Bombay High Court saying that the Gosikhurd irrigation project will be completed by March 2022.

The biggest irrigation project in Vidarbha, located in Bhandara district, is expected to irrigate over 2.5 lakh ha in Bhandara, Nagpur and Chandrapur districts.

VIDC gave a detailed progress report on all 312 projects under construction in the region. It said 102 were competed and 132 were near completion. Among major projects, Bawanthadi will be completed by December 2018, Khadakpurna by March 2019, Lower Wardha by March 2020, Bembla by 2021 and Lower Pedhi by December 2020.

Regarding the Gosikhurd irrigation project, VIDC has created an irrigation potential of 74,476 ha. The remaining will be created as follows: 31,543 ha in 2018-19; 72,393 in 2019-20; 40,000 ha in 2020-21 and 32,392 ha in 2021-22.

The project has two major canals -- right and left bank having five lift irrigation schemes on them. There are 85 submergence villages, 51 in Nagpur and 34 in Bhandara, to be rehabilitated in threes stages at 64 sites.