Illustrative image – not actual.The Forest Department of Maharashtra has waived off the condition of compensatory afforestation citing that no tree is to be cut inside the Sanjay Gandhi National Park (SGNP) for the Goregaon-Mulund Link Road project.
The Brihanmumbai Municipal Corporation (BMC) had written to the government of Maharashtra to waive off the condition of compensatory afforestation citing that no tree is to be cut inside the Sanjay Gandhi National Park (SGNP). This contention has been accepted by the state government and forwarded to the Centre.
The project now needs a final approval from a regional expert committee. The BMC has set aside Rs 100 crore in Budget 2019-20 for the project, which is estimated to cost Rs 3,000 crore.
The road will be 14 km long and consist of a 4.7 km underground tunnel passing underneath the SGNP. It will begin at Oberoi Mall and end at the Eastern Express Highway beyond Nahur station.
The BMC required multiple clearances for the underground tunnels and the most crucial one, that of the National Board of Wildlife, came in February 2019. The next step was to get a clearance from the State Forest Department. The tunnel’s entry and exit are outside forest limits, and they do not require air vents.