Illustrative image – not actual.The Union government has officially announced that it would be completing the Golden Quadrilateral project by December 2006. This was one of the important announcements made in the Outcome Budget tabled in Parliament on 25 August 2005.
The road ministry has indicated that it would finish upgradation of all 5,846 km of highways under GQ by December 2006, that, is a year after the official deadline of its completion-- December 2005.
As on July 31, 2005, it has finished four-laning of 4,944 km of the GQ, while 902 km are under implementation. GQ represents Phase I of the National Highway Development Programme.
The ministry has also projected that it would commission the the North-South East-West corridor (NS-EW) by its official deadline of December 2007. As of 31 July 2005, government has completed four-laning of only 777 km, out of the total of 7,300 km under the scheme. Stretches totaling 2,766 km are still under implementation.
NHAI had terminated eight contracts, seven of them last year itself. These contracts pertained to important stretches of NHDP and even ministry sources have said that this development has greatly hampered the progress of NHDP. Moreover, as the entire process of issuing fresh contracts takes as long as six months, and keeping in mind the current rate of progress, sources say that NSEW would be wrapped up only by middle of 2008.
Other reasons behind delay in NHDP projects, have been shifting of utilities, non-performance of contractors and local law and order problems.
The ministry has also projected that during 2005-06, it plans to spend Rs 8,800 crore for the development of national highways. While it has spent Rs.1,760 crore between April 1-June 30, 2005 (Q1), it would be spending Rs 2,200 crore, Rs 2,640 crore, and Rs 2,200 crore during the second, third and fourth quarters of the current fiscal respectively.
Apart from this, the ministry plans also stated that it would spend Rs 1,400 crore for six-laning of national highways and two-laning of expressways under Phase III A of NHDP, during 2005-06. It has spent Rs.280 crore during the first quarter, while it aims to spend Rs.350 crore, Rs.420 crore and Rs.350 crore during the second, third and fourth quarters of the current fiscal.
After the government Phase III A in March 2005, the ministry awarded contracts for six projects, covering 421 km during the same month. In April along, it had issued 14 contracts, and currently contracts are being awarded on a regular basis, the Outcome Budget stated.