Illustrative image – not actual.According to the latest status report, prepared by the Union Ministry of Road Transport & Highways, 65 per cent of the work of the 5,840-km Golden Quadrilateral (GQ) project is likely to get completed after its scheduled date of December 2003. The GQ, linking the 4 metros, forms the first phase of the National Highways Development Programme (NHDP), which is being implemented by National Highways Authority of India.
The following table shows the number of contracts that are likely to get detailed:
No. of Contracts |
Length
(kms) |
Expected
Completion |
|
|
1,074 |
Completed |
|
35 |
1,597 |
December
2003 |
|
55 |
2,575 |
December
2004 |
|
11 |
594 |
December
2005 |
The time overrun could also result in some amount of cost escalation of the project. In fact, as against the original Rs.58,000 crore cost of the NHDP (including Rs.4,000 crore of port connectivity projects) at 1999 prices, the latest project cost quoted by the ministry is Rs.60,300 crore.
A substantial portion of the projects where work is
expected to extend beyond the 2003 falls on the Kolkata-Chennai (NH-5, NH-6 and
NH-60) and the Delhi-Kolkata (NH-2) sections.
In the Kolkata-Chennai section, 24 contracts
entailing multi-laning of 913 kms are expected to be completed by December 2004,
while on the Delhi-Kolkata (NH-2), 10 contracts for multi-laning of 607 kms are
likely to be completed by end of 2004 while 10 more contracts for upgradation
of 504 kms of sections on NH-2 is likely to be completed by December 2005.