Golden Quadrilateral: Deadline seems arduousIllustrative image – not actual.

The Golden Quadrilateral Project of National Highways Authority of India is likely to miss its extended dealine. As of 29 February 2004, out of the 5,846 km, only 2,584 km was completed, while 3,298 km was under implementation.

With only 44 per cent of the project completed thus far, it seems unlikely that the project would honour its extended deadline of December 2004.

It may be recalled that the original completion target of December 2003 was extended by a year in view of problems of land acquisition in several states.

To compound the delay, the NHAI has also been entrusted with the Pradhan Mantri Bharat Jodo Pariyojana -- a national project to four-lane 10,000 km of national highways outside the purview of the NHDP. This project was originally conceived to be implemented by the Ministry of Road Transport & Highways, but went to NHAI way early this year.