Out of the 17 JICA packages, three are fully completed; three will be fully completed within a month; and the entire project is likely to be commissioned early next year.
The three completed packages include the state-of-the-art laboratory at Margao to carry out any kind of test pertaining to water.
The second completed package is the laying of the dedicated underground cables from Sheldem substation to Selaulim pumping station (17 km) and from Verna substation to Verna pumping station (6.2 km).
Another three packages which are to be fully completed within a month are the intake treatment plant and pumping station at Selaulim for 100 MLD water. The second package is the construction and rehabilitation of the transmission mains from Selaulim to Verna pumping station (40 km). The third package nearing completion is the construction of a master balancing reservoir of 20,000 cu mtr at Verna.