Illustrative image – not actual.Kolkata based GNG Group is likely to set up an integrated cement plant with capacity of one million tpa in Meghalaya at an outlay of Rs 450 crore.
The project is likely to be developed in two phases. The Phase I of the project, estimated to cost of Rs 250 crore, is likely to go on-stream by April 2010 with a capacity of 0.6 million tpa, while the Rs 200 crore Phase II is expected to be completed in 2011.
As per sources, the group has achieved financial closure for Phase I which has a debt-equity ratio of 70:30. The company plans to fund the Phase II of the project through internal accruals.