The GMR Group's Male airport project has run into trouble as the Maldives Government has temporary halted work on a new terminal building at Ibrahim Nasir International Airport (INIA).

Construction for the new terminal was part of the airport modernisation package. It started in December 2011 and is scheduled to open in 2014.

GMR had won the airport contract when the Maldives Government headed by former President Mohamed Nasheed was in place, but the project began facing problems soon after a regime change in the country in early 2012. The dispute aggravated further after GMR moved an arbitration court in Singapore over Airport Development Charge (ADC) of $25 per passenger. The project is being implemented by GMR Male International Airport. It had signed a 25 year concession agreement with Maldives Government to upgrade and manage the airport, under which an ADC of $25 was to be levied on all outgoing passengers.