Illustrative image – not actual.GMR Infrastructure, a Bangalore-based infrastructure major, is planning to infuse Rs 1,700 crore fresh equity capital into its energy segment during the FY 13-14.
Of the total proposed fresh equity investment, GMR will plug in Rs 440 crore into the Kamalanga 1,400 MW coal-based power unit; Rs 130 crore into the Emco coal-based power unit at Warora in Chandrapur district of Maharashtra; and Rs 830 crore into the coal-based thermal power unit at Raikheda village in Raipur district of Chhattisgarh. It plans to invest Rs 15-20 crore in transmission projects in 2013.
Meanwhile, the company is planning to commission unit-II and III with 350 MW each of its Kamalanga project in July and September 2013, respectively. It also plans to commission Unit-II of Emco in July 2013.
The company had generated Rs 1,231 crore by divesting 70 per cent stake in its Singapore subsidiary. This generated amount will be utilised to fund the proposed investment plan.
Currently, GMR Energy business consists of six operating assets with a cumulative capacity of 837 MW and four generation projects under various stages of construction with an aggregate capacity of 3,788 MW.
Recently, the company commenced commercial operation of 350 MW Unit I of the Kamalanga coal-based power project and 300 MW Unit I of the Warora coal-based power project.
Also, GMR is likely to divest 74 per cent stake of three toll road projects, such as Hyderabad-Vijaywada, Hungund-Hospet and Ulundurpet.