GMR starts commercial operation of Unit I of Kamalanga power projectIllustrative image – not actual.

GMR Kamalanga Energy, on 1 Ma, 2013 started commercial operation of Unit I of Phase I of its coal-based power unit at Kamalanga in Dhenkanal district of Orissa.


Power produced from unit I has been offered to GRIDCO (Grid Corporation of Orissa), as per the long term power purchase agreement executed with it pursuant to the MoU with the state government. The Group has synchronized Unit I of Phase I of the project in January 2013.


GMR is setting up (4x350 MW) 1,400 MW coal-based power unit at Kamalanga under two phases of 3x350 MW and 1x350 MW. The entire project, spread over 1,200 acre is estimated to cost Rs 4,540 crore. Work on Unit II and Unit III of the project are in progress and are expected to be commissioned by August 2013. GMR has been allocated Rampia coal block for the project.

 