GMR notice to NHAI to exit from road projectIllustrative image – not actual.

GMR Infra has served a notice to National Highways Authority of India (NHAI) stating its “intent” to exit from the Kishangarh-Udaipur-Ahmedabad project, if it did not receive the pending environmental clearance.

The pending clearance is wiping off toll revenues of about Rs 1.7 crore a day from GMR Highways. The NHAI can allow the concessionaire to collect tolls for the project only after the environment nod comes through. Meanwhile, the Government have questioned the legality of the 15-day notice served by GMR on December 21, as there was no such provision in the concession agreement, which allows for a 90-day notice period. GMR offered to pay NHAI a premium of over Rs 600 crore a year for 26 years to win the rights to develop and operate this project.

The Kishangarh-Udaipur-Ahmedabad highway project cost is estimated at about Rs 7,500 crore, out of which GMR had planned to put in a total equity of Rs 2,200 crore. Of this, it has already infused about Rs 700 crore. The company required a debt of Rs 5,400 crore, for which it had tied up with a consortium of 22 banks.

Related Link:
Project profile

← All latest storiesBack to top →