Illustrative image – not actual.GMR Group's Ambala-Chandigarh highway project at Chandigarh was opened for public transportation on 10 December 2008.
The 35 km stretch on NH21 & NH22 was developed on BOT model with a total outlay of Rs.500 crore. The concession period for this project is 20 years and it took two and a half years to complete. The project has been completed within the time schedule agreed under the concession agreement and received its provisional completion certificate on 14 November 2008.
GMR Group won this project through an international competitive bid from the NHAI in November, 2005. The scope of work included widening of the existing 2-lanes to 4-lanes and improvement, operation and maintenance, rehabilitation and strengthening of the existing road.