Illustrative image – not actual.The GMR group has sought investors to develop its 520 MW Vemagiri power project, which would come up at Vemagiri in Andhra Pradesh. Talks are on with US and German companies to pick up equity in the project.
The project, which is being implemented by Vemagiri Power Generation, would involve setting up 370 MW of generating capacity in the first phase, while another 150 MW would be added in the second phase.
The project is expected to achieve financial closure by March 2003 and commissioning is likely to be witnessed within 27 months.
The company proposes to use locally produced natural gas as fuel for the project, which in turn is expected to bring down the tariff.
The project would be financed 70 per cent by debt and 30 per cent by equity.