Illustrative image – not actual.The GMR Group has approached IDBI Bank, the lead bank to GMR Rajahmundry Energy, to reschedule its Rs 2,600-crore loan.
The Group has also asked the lenders to allow the company to delay the commissioning of the project to April, 2014. The highly indebted Group has a debt of Rs 35,000 crore at the end of the second quarter.
The Rs 3,250-crore, 768-MW Coal-fired Rajamundry project has a loan component of Rs 2,600 crore taken from 11 banks. GMR Infrastructure, which is the holding company of GMR Energy, is setting up a 768-MW Gas-fired power plant in Andhra Pradesh's Rajamundry district, and was scheduled to be commissioned this April. However, the project is running behind the schedule.