Illustrative image – not actual.
GMR Hyderabad International Airport has commissioned a 5 MW solar power plant for its captive consumption. GMR intends to increase the capacity to 30 MW over the next two-three years.
The solar plant set up with an outlay of Rs 25 crore has started generating around 25,000 units per day to meet the airport's peak power demand during day time. The plant set up in four months is designed to meet about 30 per cent of the airport’s terminal requirement.
The solar power plant has over 16,000 modules of solar panels, each having a fixed tilt for maximum sun exposure. The Grid-connected system would be used for captive consumption of the airport.