GMR commences operation of Kamalanga Unit-II Illustrative image – not actual.

GMR Kamalanga Energy has commenced operations at Unit-II of its coal-based thermal power plant at Kamalanga in Dhenkanal district of Orissa. The unit has 350 MW capacity.

 

The GMR Group is establishing a 3 x 350 MW (1,050 MW) coal-based thermal power plant at Kamalanga. Unit-I of the project, with 350 MW capacity, had commenced generation in April 2013.

 

Power produced from the plant is being supplied to Gridco in Orissa as per the long-term power purchase agreement (PPA). Besides Orissa, the company will supply power to Haryana, Bihar, and other parts of the country.

 

The company has secured coal linkage for its entire project by signing fuel supply agreements with Mahanadi Coalfields.

 

With the commissioning of Unit-II of the project, the GMR Group's combined generation capacity has touched 2,136 MW.

 