Illustrative image – not actual.Gujarat Industries Power Company is planning to raise Rs.800 crore debt for financing the capacity enhancing programme of Surat Lignite Power plant. The Rs.997.2 crore project would double the capacity of the plant to 500 MW.
The expansion project is proposed to be financed on a debt-equity ratio of 70:30. About Rs.800 crore of debt and Rs.220 crore of equity would be sourced through market and around Rs.125 crore would come from internal accruals and promoter's contribution. The project is expected to be commissioned before the end of the Tenth Five Year Plan.
The company currently has total capacity of 555 MW, which includes 145 MW gas based power station and 160 MW dual fuel fired power station on the outskirts of Vadodara as well as 250 SLPP at Nani Mangrol in Surat.