Illustrative image – not actual.Gujarat Industries Power Company (GIPCL) has successfully synchronized SLPP Phase- I, Unit-I of 125 MW.
A new generator stator has been procured from BHEL at the ex-works price of Rs 15.65 crore. After receipt of the stator at GIPCL, SLPP site on March 24, 2015, and completion of re-erection work, the machine was synchronized with the grid on 3 April, 2015. With the synchronization, it has started pumping power to the grid.
Gujarat Industries Power Company is engaged in the business of power generation. Apart from power generation, it is also engaged in conducting research and development operations such as identification.