Illustrative image – not actual.Goa Industrial Development Corporation (GIDC) has received environmental clearance from Ministry of Environment & Forest (MoEF) Department for coal block allotted in Raigarh district of Chhattisgarh.
It will start actual coal mining once it receives forest clearance from MoEF. After that, it will have to obtain a mining lease from the Chhattisgarh Government. The total area of land acquired in 2008 by the Goa Government is 639 ha, whereas the projected area is 714.35 ha.
The state government intends to get 1,800 MW power through this coal block. It has appointed power project development agency, K S K Energy Venture, for setting up a power project. NMDC was appointed by the state government for mineral production requirements of the project. However, since there was no response from NMDC, GIDC is now seeking appointment of a new mineral producer for the project.