GIDA's bridge project to be ready by October 2003Illustrative image – not actual.

According to reports, Goshree Islands Development Authority’s (GIDA) bridge project in Kerala is expected to be ready by October 2003, if the current pace of progress is maintained.

 

The project, which is estimated to cost Rs.39.37 crore, envisages construction of 3 bridges connecting the 3 islands, of Vypeen, Vallarpadam and Bolghatty to the Ernakulam mainland. The total length of these bridges would be 1,427.45 metres. The project also involves laying of roads for a distance of 2,011 metres.

 

Land acquisition at Bolghatty had been completed and handed over to the Cochin Port Trust, while the acquisition at Vypeen island had also been completed and would be handed over soon.

 

Piling has been completed for the bridge linking Ernakulam with Bolghatty, while piling work for the second and third bridges are on.

 

The road formation works have also started. Vallarapadam road work is moving at a faster pace. Girder castings are also going on and the first girder is expected to be placed by November 2002.