Illustrative image – not actual.Reliance Industries (RIL) has
opted out of the 375 MW Ghogha power project in Gujarat paving
way for Nirma to develop the project.
The project envisages the installation 3 lignite based generating
units of 125 MW each in Bhavnagar district.
Reliance, which was selected to implement the project, was keen
to utilise petro-coke from its Jamnagar refinery, as feedstock.
But, RIL failed to convince Gujarat Electricity Board to enter
into a power purchase agreement. Further, it wanted to re-assess
the quality and quantity of lignite from the mines.
The project is now likely to be implemented by Nirma and Gujarat
Power Corporation, through a 49:51 joint venture. Since Nirma
would be a minority stakeholder, certain unfavourable provisions
of the Gujarat Infrastructure Development Act, can be
circumvented.