Ghiri small hydro project by July 2007Illustrative image – not actual.

Himalayan Crest Power is expected to complete its 3 MW hydropower power project on Ghiri River in Sirmaur district of Himachal Pradesh by July 2007.

Around 90 per cent of the project activity was completed, company officials told ProjectsToday. The project would entail an investment of Rs.17.47 crore. Local company, Shanti Flat & Foundation (P) Ltd, is the civil contractor for the project.

Another small hydropower project of Himalayan Crest Power, the 2x1.5 MW Timbi small hydel power project in Sirmaur district is complete to the extent of 75 per cent. Full completion is scheduled for December 2007.