Ghana is set to receive finance worth USD 212 million from the Millennium Development Authority (MiDA) for a series of projects and initiatives to modernise the country’s power distribution sector.

MiDA will commit the funds in the third year of the compact toward enhancing the country’s power distribution infrastructure and technology as a strategic decision to turn around operations of the power distributor. MiDA is currently finalising negotiations toward construction of the biggest Bulk Supply Point (BSP) at Pokuase, which is likely to start by March 2019.

Additionally, four primary substations which will feed on the BSPs to be situated at Kotobabi, Korle-Gonno, Achimota and Kanda will be established. MiDA is also looking at refurbishing the existing power lines at various power stations as a way of tackling the power losses from wastage and illegal tapping.