The National Hydroelectric Power
Corporation (NHPC) has been engaged as the nodal agency for exploitation of
geothermal energy in the country by Ministry of Non-Conventional Energy Sources
(MNES). NHPC has been assigned the work of installation of pilot geothermal
power plant in Tattapani Geothermal Fields, Chhattisgarh followed by
Exploration for mega watt size power plant. For the pilot plant, MNES would
provide funds to the tune of Rs.4.6 crore.
"Geothermal Energy" is the
vast reservoir of heat energy stored in the earth’s interior. Its surface
manifestations are volcanoes, fumaroles, geysers and hot springs. The
Geothermal Energy is literally the heat content within the earth and the term is
generally used for the earth’s heat that can be or could be recovered and
exploited by man. It originates from the earth’s molten interior called magma
and the decay of radioactive materials. Heat flows out because of the massive
temperature gradient between the surface and interior.
In India, studies for locating this
renewable energy resource were taken up by Geological Survey of India (GSI) for
nearly the past three decades. As a result, about 340 hot springs were located
in many parts of the country. Some of the major geothermal pockets where these
hot springs are located are Himalayan Province, Son-Narmada-Tapi Province, West
Coast and Cambay Province, Andaman & Nicobar Province. As per the existing
studies, the potential areas for development of geothermal energy for power
generation are Puga and Manikaran (Himalayan Province) and Tattapani
(Son-Narmada-Tapi Province).
Since technology is not available with
NHPC and elsewhere in the country for tapping this renewable source of energy,
the NHPC has hired a renowned International Consultant in the field of
geothermal power generation – who will help NHPC to prepare Detailed Project
Report (DPR) for a number of potential sites. Further, to develop in house
technology a delegation is being deputed to the United States to acquire
technology, where about 2,800 MW power is generated by this energy.
The Chhattisgarh Government has granted
permission for installation of pilot geothermal power plant at Tattapani. Land
is being acquired and field exploratory and preparatory works at Tattapani have
been started. NHPC is also interacting with the Oil and Natural Gas Commission
and various other organisations to undertake drilling work. The NHPC is
endeavouring to start generation within the next one and a half years and thus
bring India on the world map of geothermal power generation.