Illustrative image – not actual.The project is estimated to cost Rs 138 crore. The project comprises four buildings of G+10 floors each with 119 Type-II, 100 Type-III, 60 Type-IV, 30 Type-V and five Type-VI GPRA quarters with various modern amenities. In 2016, DEC Infrastructure and Projects was appointed as the contractor to execute the project. In the same year, all necessary clearances were received and civil work commenced with an intention to complete the project by December 2018.
According to the latest information collected by Projects Today, Electrical and Mechanical (E&M) services was under installation stage with completion scheduled for February 2019. At present, internal painting and finishing work was underway on all four buildings.
Completion date for building 1 and 2 was re-scheduled for January 2019 and for buildings 3 and 4 has been re-scheduled for March 2019.