Illustrative image – not actual.General Motors is actively considering Maharashtra as the location for its proposed greenfield automobile project. A GM team has already conducted soil investigation at Talegaon (Pune district) and a series of meetings between the company and state government officials have already been held.
GM has shortlisted Maharashtra and Tamil Nadu as possible locations for its 2 lakh cars per year plant targeted to commission by 2010. The plant will essentially produce Chevvy Spark - a small car.
The US-based automobile giant already has a plant at Halol in Gujarat where capacity is being significantly enhanced to 85,000 cars per year from the current 65,000 cars per year. The Halol plant that began operations with a capacity of 25,000 cars per year saw a major capacity ramp-up in April 2005.
GM has so far spent Rs.1,200 crore on its Halol plant and is investing another Rs.150 crore for the capacity expansion to 85,000 cars per year.