Illustrative image – not actual.
GE Power India has secured orders worth Rs 467.9 crore exclusive of taxes (i.e. around USD 68.3 million) from Bharat Heavy Electricals (BHEL).
The contract bagged is for twin boiler equipment for supercritical thermal power projects in Patratu and Udangudi.
The company is executing Phase-I expansion of Patratu Vidyut Utpadan Nigam’s (PVUNL) 2.400 MW (3x800 MW) supercritical thermal power station at Patratu on engineering, procurement and construction (EPC).
Apart from this, it is also executing first stage of a proposed 1,320 MW supercritical thermal power plant at Udangudi by the Tamil Nadu Generation and Distribution Corporation (TANGEDCO).
The company will also supply pressure parts equipment for the Patratu project at an order value of around Rs 341.5 crore exclusive of taxes (i.e. approximately USD 49.8 million) and to Udangudi thermal power projects at a value of approximately Rs 126.4 crore exclusive of taxes (i.e. approximately USD 18.5 million) for onshore supply.