Illustrative image – not actual.The Union Minister for Power, Mr Suresh Prabhu augmented the 500 MW Gazuwaka HVDC project in Andhra Pradesh on 22 February 2002.
The project is estimated to cost Rs.769 crore and is
scheduled for commissioning in 2004-05.
The highlights of the project are:
Ø
500 MW HVDC back-to-back module at Gazuwaka
Ø
Construction of Gazuwaka-Vijaywada 400 kV D/C series
Ø
Compensation on existing Jeypore-Gazuwaka 400 kV D/C
Ø
Rengali-Indravaiti 400 kV S/C and Meramyndale-Jeypore
400 kV S/C lines
The project would enable optimal utilisation of
surplus power in the eastern region and help in meeting power deficit in the
southern region.