Illustrative image – not actual.Gayatri Projects won two orders worth Rs 89.86 crore.
The first Rs 68.09-crore order was awarded by Tecpro Systems, for civil engineering works for the coal handling plant of NTPC - BRBCL for 4x250 MW power plant at Nabinagar in Bihar. The contract work should be completed within a period of 30 months from the date of commencement.
The second order worth Rs 21.77 crore is from NALCO for civil and structural works for additional coal storage and handling system required for Phase II expansion (2x129 MW- units 9 and 10) of the captive power plant at Angul, Orissa. The contract work should be completed within a period of 12 months from the date of commencement.