Illustrative image – not actual.Dutch dredging company Royal Boskalis Westminster and the Belgium-based Dredging International (DI) have floated a 50:50 joint venture to set up a trench for pipelines to an offshore gas field KG-6 in Bay of Bengal from RIL's terminal near Kakinada. The project, which will be carried out for Switzerland-based Allseas Group, is valued at about Rs.730 crore.
This move will expedite commercial production of KG gas and link the gasfield to the 1,400-km East-West pipeline for the transportation of gas to the western coast by June 2008. Gas from D-6 block in the KG basin will first flow to onshore terminal near Kakinada and from there it will be pumped to 1,400-km East-West pipeline and other pipelines.
Work on the trench will commence in September 2007 and is scheduled to be completed by June 2008. The scope includes an 18 metre-wide, 21 km long trench for positioning nine pipelines that will pass through the Godavari river for the mainland connection of the offshore field.
RIL is awaiting government directives on the pricing of natural gas from KG basin to enter into firm supply agreements with consumers. Reliance Gas Transmission Infrastructure (RGTIL) is executing the pipeline project for RIL. Besides the East-West pipeline, RGTIL is executing Kakinada-Haldia pipeline, Kakinada-Chennai and Chennai-Mangalore pipeline projects. RIL's development of the gas discoveries is on schedule for production and supply of gas by 2008.
All major EPC/EPIC contracts have been awarded and all long lead items have been ordered. The pre-engineering survey for offshore installation has been completed. Currently, the project is in the fabrication phase and scheduled and the construction jetty has been completed. Detailed engineering of the onshore terminal is nearly 50 per cent complete.