Gargi dam project to be operational by May 2029Illustrative image – not actual.

Chief Minister Devendra Fadnavis has directed officials to expedite rehabilitation, afforestation, and construction activities to ensure timely completion of the project.

The project, coming up in the Western Ghats, is estimated to cost Rs 3,065 crore. Approximately 844 hectares of land will be affected, including 186 hectares of private land and 658 hectares of forest land, while the submergence area will cover 805 hectares.

Several statutory approvals have already been obtained, including clearances from the Ministry of Tribal Affairs (MoTA), the National Committee on Seismic Design Standards, and the relevant authorities for project design and environmental approvals. Approval from the National Board for Wildlife is currently under process.

During the review meeting, the Chief Minister also reviewed the proposed Navi Mumbai Airport Influence Notified Area (NAINA) Township project. He directed officials to immediately approve the development plans for villages within the NAINA area, rectify errors in land records, and expedite the distribution of property cards to eligible villagers.

← All latest storiesBack to top →