Illustrative image – not actual.Nearly two weeks after being returned to the civic administration over cost concerns, the Gargai dam project in Ogada village, Palghar district, is set to be presented again before the BMC Standing Committee for approval.
The contractor, Soma consortium, which had initially quoted 10.9 percent above BMC’s estimate of Rs 3,006 crore, has now agreed to reduce the bid to Rs 3,276 crore—nearly two percent above the original estimate, saving around Rs 269 crore. The committee had earlier rejected the steep contract value, prompting three rounds of negotiations. Officials stated that execution risks were already factored in, leaving little justification for the initial higher quote. The project still requires key clearances from the Central Wildlife Board and forest departments at both state and Central levels.
The construction plan spans three years: the first year will focus on securing permissions and preparing infrastructure to relocate six affected villages, the second year will see dam construction, and the third year will involve installation of electrical systems, including a 1,200 kW hydropower unit to offset electricity costs. Once completed, the Gargai dam will add 440 million litres per day to Mumbai’s water supply, marking the first new reservoir since the Middle Vaitarna project and targeting completion by 2029.