Gangavaram Port to commence operations by April 2008Illustrative image – not actual.

Work on Gangavaram port in Visakhapatnam district of Andhra Pradesh is likely to commence operations by April 2008.

So far, 75 per cent of the dredging works, 60 per cent civil works and 50 per cent of breakwater works have been completed. While L&T is carrying out the civil and breakwater works, dredging is being undertaken by Dredge International. Spain-based Durofiligra has bagged the mechanical equipment supply contract and the first consignment is likely to arrive by end-November 2007.

In the first phase, the port is constructing five berths to handle iron ore, coal and other bulk cargo with an investment of about Rs.2,000 crore. The state government, which has been offered 11 per cent equity in the project, has allotted 24,00 acres of land. The port is laying a 3.5 km long conveyer belt from the berth to Visakhapatnam Steel Plant to move iron ore and coal besides constructing deep draft berths to handle up to 2 lakh DWT (deadweight tonnage) vessels.

Also See:

L&T bags EPC contract for Gangavaram Port (26-Dec-05)

Related Links:
Project profile

← All latest storiesBack to top →