Ganga Riverfront project likely to be completed by June 2018Illustrative image – not actual.
The state government of Bihar has set the target to complete the beautification work on the 20 Ganga ghats in Patna, under the World Bank-aided Ganga Riverfront project by June 2018.

The project was initially slated to be completed by June 2016. It entails development of the 5.7 km long and 15 ft wide walkway along the 20 ghats, with decorative street lamps, public lavatories, 500 seating benches and green cover.

Bihar Urban Infrastructure Development Corporation (BUIDCo) has already completed work on 12 ghats, including B N College Ghat, Anta Ghat, Misri Ghat, Rani Ghat, Pathari Ghat and Alamganj Ghat.

Besides, around 4.5 km out of the 5.7 km of the walkway has also been constructed.

Work on the remaining eight ghats is in an advanced stage of completion. The corporation is committed to completing the project by June 2018 after which the project will be handed over to Patna Municipal Corporation.

The project will be developed at an estimated outlay of Rs 254.52 crore based on a 70:30 cost sharing model between the centre and the state. The World Bank has contributed 90 percent in the centre's share, which comes to 63 percent of the total project cost.

The project divides the 20 ghats into four urban precincts. Precinct-1 covers the riverfront between Collectorate Ghat and Mahendru Ghat. Precinct-2 covers the riverfront between Mishri Ghat and Patna College Ghat. Precinct-3 covers the riverfront between Gandhi Ghat and Rani Ghat and Precinct-4 covers the riverfront between Bhadra Ghat and Nauzar Ghat.