Ganga driveway project to be delayed by 2 yearsIllustrative image – not actual.

The Ganga driveway project will get delayed by at least two years from its earlier commissioning year of 2017.

The 23.5 km long  project, which after completion will ensure hassle-free movement between west and east Patna, has hit a roadblock because of delay in land acquisition.

Navayuga Engineering Company, which is executing the Rs 3,160 crore project, has requested the state to extend the project deadline.

The Bihar State Road Development Corporation (BSRDCL), a wing of the road construction department, which had awarded the construction work to Hyderabad-based Navayuga Engineering Company, has received the application to extend the deadline of the project from the executing firm.

Delays in land acquisition is likely to escalate the project cost to Rs 3,500 crore.