Illustrative image – not actual.The Gandhipuram two-tier flyover project is expected to be ready in 2017.
On 8 November, 2014, the State Highways Department said that the work on this project started in July this year and it is scheduled for completion within 33 months (April 2017). However, the aim is to complete the flyover work before 2017.
The two-tier flyover project in Gandhipuram has two segments.
It includes a four-lane flyover for 1.75 km from Nanjappa Road (near Park Gate junction) that will end near the omni bus stand (Sathyamangalam Road). In addition, it will also have a seven-metre wide service lane on either side on Nanjappa Road and two subways (pedestrian crossing). The lane will be at Gandhipuram junction and another near the mofussil bus stand.
The second-level flyover will be a two-lane one for 1.22 km. It will start near the seventh cross on 100-feet road and end near the Avarampalayam junction.
For this flyover project, the land acquisition is minimum and use of modern construction method has resulted faster work.