Gammon Infrastructure Projects is likely to commence construction work soon on its offshore container terminal project at Mumbai Port Trust.

 

The company invited bids for long-pending dredging work. International Seaport Dredging emerged as the lowest bidder with a quote of Rs 268 crore when the bids were opened last week. Other contractors, who submitted bids for the project were Dharti Dredging and Van Oord. The work will be awarded in another 15-20 days, as there are some administrative approvals pending. It is expected to take about eight months to complete from the date of commencement.

 

The container terminal project is being developed by a JV -- Indira Container Terminal. The JV was floated by Gammon and Dragados of Spain. The project was scheduled to be commissioned by 2010. As a result of delay, the estimated cost of the project escalated from the initial Rs 1,012 crore to about Rs 1,800 crore.

 