Gammon Infra's terminal hangs in balanceIllustrative image – not actual.

More than 10 years after it was awarded, the much delayed and incomplete Offshore Container Terminal (OCT) project at Mumbai Port will go for a rebidding.

The Rs 1,200 crore project, to be developed jointly by Gammon Infrastructure and Dragados SPL of Spain, for a concession period of 30 years on Build-Operate-Transfer basis, is nowhere near completion. After Dragados withdrew from the project, Gammon Infra was developing the project on its own.

The bidding process is likely to get finalised by March 2017.