Illustrative image – not actual. National Highway Authority of India has awarded a Rs.580
crore project to Gammon-Sadbhav-Billimoria consortium. The project involves
four-laning of a 100 km highway between Vadape and Gonde on NH-3 in Maharshtra.
The project was awarded on BOT basis to the Gammon-Sadbhav-Billimoria consortium
on 16 June 2005. The equity participation of Gammon, Sadbhav, and Billimoria is 70:20:10 ratio
respectively, it is learnt. Work on the project is likely to start in
January 2006 with envisaged completion by January 2009.
NHAI aims to finalize the four-laning of a 36-km stretch of NH 21 and NH 22 between Ambala and Chandigarh with a project cost of about Rs.298 crore, during July 2005. Tenders for the project that has a gestation period of 30 months have been received.
ProjectsToday adds:
It may be mentioned that NHAI had opened bids
for the Vadape-Gonde section on 31 March 2004, but bids were not awarded then.
Same has been the case of the 118 km Dhule-Pimpalgaon section in Maharashtra for
which Ircon International emerged as the successful bidder. There is no news
about Ircon's official appointment.